2 Jun
Posted by Joshua.
The before shot of the kitchen. We had already removed two different shelving units and the dinning room table. (Sorry for the mess)
11 Photos
Day 1 included demo and electrical work.
5 Photos
Day 2 included hanging sheetrock, installing recessed lighting, a new laundry room door, and a new kitchen window.
9 Photos
Day 3 included sanding the sheetrock, moving an A/C vent, and installing backerboard for the tile.
8 Photos
Day 4 included painting, installing a new door to the garage, and laying tile.
6 Photos
Day 5 included grouting the tile, installed transition pieces, and paint touch-ups.
After a week off between contractors, Day 15 included installing the cabinets and some crown molding.
Day 16 included installing the cabinet doors, shelves and more crown molding.
7 Photos
Day 17 included installing the remaining cabinet doors, shelves and crown molding.
14 Photos
Days 25 and 26 included installing the remaining crown molding, countertops, trim, sink, dishwasher, stove, microwave range hood, and refrigerator.
Your email address will not be published. Required fields are marked *
Name *
Email *
Website
Comment
You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>